Jamieson Road Fire Hall: Council-ready in 16 weeks

Municipal District of Bighorn No. 8, Alberta · 2025

16 weekskickoff to an early (Class D) estimate
3 optionscosted side by side
~$1.0Min site costs clarified before Council
Council-readydecision package
ClientMunicipal District of Bighorn No. 8, Fire Department
FacilityNew 7,924 sf fire hall, 3 apparatus bays, post-disaster
Mexsig roleProject manager, Phase 1 front end
TimelineKickoff May 2025. Class D estimate on three options issued August 2025.
Class DAn early, pre-design cost estimate based on a space program and site information, used to compare options and set a budget range.
StatusPhase 1 complete; Council-ready package delivered.

The challenge

The Jamieson Road hall was built in the 1990s for two apparatus. The department now runs three. There was no room for decontamination, training or storage. The District wanted to move quickly and needed a defined scope and budget first.

The existing two-bay Jamieson Road fire hall among aspen and spruce, May 2025

The existing hall, May 2025. Photo: MEXSIG Inc.

The outcome

"Your team got us from zero to having a Council package ready for review and approval."Rob Duffy, Fire Chief, Municipal District of Bighorn No. 8

Status

Phase 1 is complete. The District has a Council-ready package, a defined scope and a de-risked site, so the next phase can start from known numbers.

Project team

Sigfrido Pacheco-Vega, P.Eng., PMP, LEED AP (project manager) · Greg Wilkes, former Deputy Chief, Calgary Fire Department (fire station SME) · Mark Ruault, P.Eng. (civil, site and utilities) · Catherine Booth (project coordination)

Planning a fire hall or a municipal capital project?

Call Sig directly. A first conversation about scope, budget and funding costs nothing. We reply within one business day.

Call 587.830.1371Email Sig